Phase 1 timeline 

key-milestones

Assuming that fundraising targets are reached, a timeline for the project can be summarised as: 
 

  2019  
  March Formal internal launch of the project
   First capital appeal launched
  May Formal external launch of the project
  July Purchase land strip from council
  October Application for planning permission submitted 
   
  2021  
  March / April Second capital appeal
   
  2022  
  Spring Work commences on site
   
  2023  
  March / April Third capital appeal
  Spring Building work completed
  June Formal opening of phase 1
  July Fundraising begins for phase 2